The Heroes Foundation · Transforming Together Initiative Phase 2 · Mayaro Pilot

Progress Report

—

Amber · re-baseline proposed
Shared objective

Find out what would most improve life for the average Mayaro resident, at every stage from early childhood to young adulthood, and line up development support behind it.

Led by The Heroes Foundationbringing government, business, civil society and the community behind one plan for Mayaro.
Overall
AmberEarly work done; ToR dates need resetting
Actions to date
——
Next deliverable
——
Timeline
——

Progress to date

    Decisions needed from Heroes

    1. Approve the proposed scheduleToR dates need a written variation. Signing off the methodology by 23 Dec brings completion forward by about a week.
    2. Nominate a safeguarding focal pointNeeded now for approvals, and before any contact with young people or families.
    3. Confirm the approved data repository and access controlsRequired before fieldwork; protects participants and partners.
    4. Authorise introductions to prospective partnersTo align the evidence base and avoid duplicating existing research.

    Next two weeks

    • Inception audit of Phase 1 records30 Nov – 4 Dec
    • D1 Inception report + workplanFri 4 Dec
    • Stakeholder register built from the NGO list30 Nov – 11 Dec
    • Data-governance, safeguarding and permissionsfrom 30 Nov
    • Evidence review and research toolsfrom 7 Dec

    Schedule recovery

    Against a 1 Nov start, D1 (Wk 2) is overdue and D2–D3 fall due this week. Keeping the original sequence would also have put fieldwork over Christmas.

    Proposed: D1 on 4 Dec, fieldwork 11–29 Jan (after the holidays, before Carnival), completion —. The groundwork already done, including the NGO list, data-protection terms and a local survey pipeline, shortens the early phases.

    Plan and where we are

    Started Sun 1 Nov 2026. Shows the proposed schedule; the dotted line marks the original 12-week ToR end.

    Deliverables

    Original ToR week against the proposed date.

    Field team to hire

    Locally recruited, shortlisted from the Mayaro cohort and candidate list; every contract carries confidentiality, consent and data-protection terms.

    RoleCountWindow
    Fieldwork Coordinator: local networks, scheduling, custodian of the consent register114 Dec – 5 Feb
    Senior Qualitative Researcher: KII/FGD design, leads interviews with senior stakeholders17 Dec – 29 Jan
    Community Enumerators / Note-takers3–47 Jan – 5 Feb
    Youth FGD Facilitator: must not also be school staff1–27 – 29 Jan
    Safeguarding Officer: supplied by Heroes, 0.2 FTE; needed for approvals—from 30 Nov