Transforming Together Initiative — Mayaro Pilot Phase 2 · draft timeline

The Heroes Foundation · 12-week consultancy · anchored to a notional start of Mon 30 Nov 2026 (Wk 1). Re-anchor on contract signature; week offsets hold.

Master plan

gantt
    dateFormat YYYY-MM-DD
    axisFormat Wk %W
    section A Inception
    Document audit + status check      :a1, 2026-11-30, 7d
    Data-governance & permissions      :crit, a2, 2026-11-30, 14d
    D1 Inception report + workplan     :milestone, a3, 2026-12-11, 0d
    section B Stakeholders
    Register update + categorisation   :b1, 2026-12-01, 14d
    Consultations + engagement log     :b2, 2026-12-08, 14d
    D2 Mapping report                  :milestone, b3, 2026-12-22, 0d
    section C Methodology
    Evidence review + source inventory :c1, 2026-12-07, 14d
    Tools, sampling, consent, safeguarding :c2, 2026-12-07, 14d
    D3 Research toolkit                :milestone, c3, 2026-12-22, 0d
    section D Fieldwork
    KIIs FGDs + supervision            :d1, 2026-12-28, 21d
    QA + cleaned de-identified dataset :d2, 2027-01-11, 14d
    D4 Dataset + fieldwork summary     :milestone, d3, 2027-01-22, 0d
    section E Mapping
    Programme inventory + pathway matrix :e1, 2027-01-04, 21d
    D5 Gap/overlap report              :milestone, e2, 2027-01-29, 0d
    section F Analysis
    Triangulation + situational report :f1, 2027-01-25, 14d
    D6 Situational analysis            :milestone, f2, 2027-02-05, 0d
    section G Forward plan
    Operational model + MEL framework  :g1, 2027-02-01, 14d
    Validation session                 :g2, 2027-02-08, 7d
    D7 Framework + forward plan        :milestone, g3, 2027-02-19, 0d
    section H Closeout
    D8 Final report + handover         :milestone, h1, 2027-02-19, 0d

Critical path: data-governance & permissions → fieldwork. The ToR blocks sensitive fieldwork until permissions, safeguarding protocols and secure data arrangements are confirmed.

Field staffing & interview track

gantt
    dateFormat YYYY-MM-DD
    axisFormat W%W
    section Consultant
    Inception audit + workplan         :a1, 2026-11-30, 14d
    Evidence review + research design  :a2, 2026-12-07, 21d
    KII/FGD guides + consent forms     :a3, 2026-12-14, 14d
    section Approvals
    Safeguarding + data permissions    :crit, g1, 2026-11-30, 28d
    SAC/Heroes methodology sign-off    :crit, g2, after a3, 7d
    section Field Team
    Recruit + shortlist enumerators    :h1, 2027-01-04, 7d
    Contract + consent vetting         :h2, 2027-01-08, 5d
    Facilitator training (2-3 days)    :h3, 2027-01-11, 3d
    section Fieldwork
    KIIs govt/schools/providers        :f1, 2027-01-18, 18d
    FGDs youth + parents/caregivers    :f2, 2027-01-18, 18d
    Community consultation events      :f3, 2027-01-25, 11d
    Daily QA + de-identified logging   :f4, 2027-01-18, 21d
    section Wrap
    Cleaned dataset + fieldwork summary :w1, 2027-02-08, 7d
    D4 delivery                        :milestone, w2, 2027-02-15, 0d

Deliverables

#DeliverableToR week
D1Inception Report + Detailed WorkplanWk 2
D2Stakeholder Mapping & Engagement ReportWk 4
D3Needs Assessment Methodology + Research ToolkitWk 4
D4Community Assessment Dataset + Fieldwork SummaryWk 8
D5Programme, Resource & Development Pathways Mapping ReportWk 9
D6Comprehensive Situational & Needs Analysis ReportWk 11
D7Pilot Operational Framework & Forward PlanWk 12
D8Final Consultancy Report, Presentation & HandoverWk 12

Field team to hire

RoleCountWindow
Fieldwork Coordinator (local networks, consent register custodian)1Wk 6–11
Senior Qualitative Researcher (KII/FGD design, leads hard interviews)1Wk 3–9
Community Enumerators / Note-takers3–4Wk 7–10
Youth FGD Facilitator (no dual school-staff role)1–2Wk 8–10
Safeguarding Officer (Heroes-supplied, 0.2 FTE) — gates fieldwork—from Wk 8