The Heroes Foundation · 12-week consultancy · anchored to a notional start of Mon 30 Nov 2026 (Wk 1). Re-anchor on contract signature; week offsets hold.
gantt
dateFormat YYYY-MM-DD
axisFormat Wk %W
section A Inception
Document audit + status check :a1, 2026-11-30, 7d
Data-governance & permissions :crit, a2, 2026-11-30, 14d
D1 Inception report + workplan :milestone, a3, 2026-12-11, 0d
section B Stakeholders
Register update + categorisation :b1, 2026-12-01, 14d
Consultations + engagement log :b2, 2026-12-08, 14d
D2 Mapping report :milestone, b3, 2026-12-22, 0d
section C Methodology
Evidence review + source inventory :c1, 2026-12-07, 14d
Tools, sampling, consent, safeguarding :c2, 2026-12-07, 14d
D3 Research toolkit :milestone, c3, 2026-12-22, 0d
section D Fieldwork
KIIs FGDs + supervision :d1, 2026-12-28, 21d
QA + cleaned de-identified dataset :d2, 2027-01-11, 14d
D4 Dataset + fieldwork summary :milestone, d3, 2027-01-22, 0d
section E Mapping
Programme inventory + pathway matrix :e1, 2027-01-04, 21d
D5 Gap/overlap report :milestone, e2, 2027-01-29, 0d
section F Analysis
Triangulation + situational report :f1, 2027-01-25, 14d
D6 Situational analysis :milestone, f2, 2027-02-05, 0d
section G Forward plan
Operational model + MEL framework :g1, 2027-02-01, 14d
Validation session :g2, 2027-02-08, 7d
D7 Framework + forward plan :milestone, g3, 2027-02-19, 0d
section H Closeout
D8 Final report + handover :milestone, h1, 2027-02-19, 0d
Critical path: data-governance & permissions → fieldwork. The ToR blocks sensitive fieldwork until permissions, safeguarding protocols and secure data arrangements are confirmed.
gantt
dateFormat YYYY-MM-DD
axisFormat W%W
section Consultant
Inception audit + workplan :a1, 2026-11-30, 14d
Evidence review + research design :a2, 2026-12-07, 21d
KII/FGD guides + consent forms :a3, 2026-12-14, 14d
section Approvals
Safeguarding + data permissions :crit, g1, 2026-11-30, 28d
SAC/Heroes methodology sign-off :crit, g2, after a3, 7d
section Field Team
Recruit + shortlist enumerators :h1, 2027-01-04, 7d
Contract + consent vetting :h2, 2027-01-08, 5d
Facilitator training (2-3 days) :h3, 2027-01-11, 3d
section Fieldwork
KIIs govt/schools/providers :f1, 2027-01-18, 18d
FGDs youth + parents/caregivers :f2, 2027-01-18, 18d
Community consultation events :f3, 2027-01-25, 11d
Daily QA + de-identified logging :f4, 2027-01-18, 21d
section Wrap
Cleaned dataset + fieldwork summary :w1, 2027-02-08, 7d
D4 delivery :milestone, w2, 2027-02-15, 0d
| # | Deliverable | ToR week |
|---|---|---|
| D1 | Inception Report + Detailed Workplan | Wk 2 |
| D2 | Stakeholder Mapping & Engagement Report | Wk 4 |
| D3 | Needs Assessment Methodology + Research Toolkit | Wk 4 |
| D4 | Community Assessment Dataset + Fieldwork Summary | Wk 8 |
| D5 | Programme, Resource & Development Pathways Mapping Report | Wk 9 |
| D6 | Comprehensive Situational & Needs Analysis Report | Wk 11 |
| D7 | Pilot Operational Framework & Forward Plan | Wk 12 |
| D8 | Final Consultancy Report, Presentation & Handover | Wk 12 |
| Role | Count | Window |
|---|---|---|
| Fieldwork Coordinator (local networks, consent register custodian) | 1 | Wk 6–11 |
| Senior Qualitative Researcher (KII/FGD design, leads hard interviews) | 1 | Wk 3–9 |
| Community Enumerators / Note-takers | 3–4 | Wk 7–10 |
| Youth FGD Facilitator (no dual school-staff role) | 1–2 | Wk 8–10 |
| Safeguarding Officer (Heroes-supplied, 0.2 FTE) — gates fieldwork | — | from Wk 8 |